Energy References
Our engineers have experience and knowledge across many aspects of projects in the Energy space, such as:
•Feasibility studies,
•Designs and construction of renewable generation, and
•Power infrastructure and grid connection works.
We have a local team of multi-disciplinary engineers with-in house access to all engineering disciplines – electrical, structural, civil, mechanical, environmental, and relevant legislation, and provide access to international experienced experts allowing us to leverage past and best practices from a global perspective. We share in their success stories at global reference sites.
Mulilo Renewable Project Development (Pty) Ltd
Struisbult PV2 55MW Solar Energy Facility
Location: South Africa, Northern Cape, Struisbult
Project start and end dates: January 2021 - ongoing
Project Description
Engineering services of a Self-build (SB) Design Engineer (Eskom Approved) to perform the Eskom Self-build Engineering Services for the Hybrid Project. The design engineer is responsible to ensure Eskom TEF approval and final design package acceptance). The services include construction monitoring during.
Services delivered
Compile an Eskom preliminary design pack for the connection of the StruisbultPV2 Solar PV Plant to the Eskom network. Present the preliminary design to the DRT at Eskom. Compile the Eskom detailed designs. Construction supervision (Optional at an owner’s engineer level).
Mulilo Renewable Project Development (Pty) Ltd
Springbok Wind Energy Facility
Location: South Africa, Northern Cape, Springbok
Project start and end dates: January 2021 - ongoing
Project Description
Springbok 55 MW Wind Energy Facility
Compile an Eskom preliminary design pack for the connection of the Springbok 55 MW Wind Energy Facility to the Eskom network.
Present the preliminary design to the DRT at Eskom.
Services delivered
Compile an Eskom preliminary design pack for the interconnection to the Eskom network.
Present the preliminary design to the DRT at Eskom.
Compile the Eskom detailed designs.
Western Cape Government
Municipal Energy Resilience Project
Location: South Africa, Northern Cape, Springbok
Project start and end dates: January 2021 - November 2021
Project Description
The objective of this project is to provide project development support and capacity building to the municipalities in the Western Cape province in South Africa, with the view to implement renewable energy projects. These projects are intended for implementation by IPPs and will provide energy resilience against power quality and tariffs, for businesses, households, and other energy users.
Services Delivered
The development of business cases for multiple renewable energy projects throughout the province. Identification of pioneering projects in candidate municipalities and the development of a project roadmap for the implementation of projects.
Royal HaskoningDHV formed part of a consortium of legal, financial, and technical consultants and provided the technical inputs in this assignment.
Samancor
Transaction Advisory Services to Establish solar based electricity and alternative generation system
Location: TubatseFerrochrome Plant, Lydenburg/Steelpoort, South Africa
Project start and end dates: Phase 1: January 2021 – Ongoing, Phase 2: January 2021 -Ongoing
Project Description
In Phase I of the project, Royal HaskoningDHV, in collaboration with Webber Wentzel and Cresco were appointed as transaction advisors to investigate the Viability of this generation solution from a Legal, financial, and technical point of view. Phase 2 is to provide Transactional Advisory Services in investigating renewable and alternative power generation for the TubatseFerrochrome plant.
Services Delivered
The advisory services reviewed solutions such as on-site solar generation, power wheeling, co-generation, and gas-to-liquid conversion of the smelter off gas. Prospective sites for solar generation were evaluated from a technical and environmental point of view. Financial calculations such as IFRS and tariff perspectives were calculated for the various technical solutions. The IPP legal and contractual matters were investigated, and advice was provided on the drafting of a Power Purchase Agreement. A framework for an IPP RFP was drafted and a strategy for the implementation of the alternative power solution was compiled. Phase II of the project includes the studies and investigations required for the preparation of an RFP document for IPP companies to submit proposals as well the adjudication thereof. A concept design for the 100MW on-site solution was compiled and the full Environmental Impact Assessment process was undertaken, including application to the Authorities.
CITRA Construction
(Element Consulting Engineers)
Butterfly Blue Renewable Energy Investigation
Location: Blue Downs, Cape Town, South Africa
Project start and end dates: January 2021 - January 2022
Project Description
A Renewable Energy investigation for the potential off-grid electrical supply to the proposed Butterfly Blue residential development. The development is situated in Blue Downs, Cape Town.
Services Delivered
After a load estimation was done, the different supply alternatives and technologies were investigated.
A comparison was done between Eskom (local supply authority) and a hybrid off-grid solution consisting of Solar PV, Battery Energy Storage and Diesel Generation.
Different development scenarios were evaluated in terms of technical and financial feasibility by comparing the Levelized Cost of Energy (LCOE) of each technology.
Consolidated Power Project (Pty) Ltd
(IPP: EPC Contractor project)
PerdekraalEast Wind Farm, High Voltage Electrical Infrastructure
Location: Western Cape, South Africa
Project start and end dates: May 2018 to March 2022
Project Description
Establishment of the Adamskraal 132 kV Substation initially consisting of one line bay, a single set of tubular bars, & one feeder (with a future footprint consisting of four linebays, a bus-section breaker, and two feeders).
Establishment of a shared substation platform (civil works and main earth grid) for the Adamskraal 132 kV Substation and the IPP 33/132 kV Substation. Construction of the Adamskraal-Kappa 132 kV overhead line (8 km, single circuit, single TERN conductors with a 48-core overhead optic fibre ground wire (OPGW) and a WOLF shield wire
Services Delivered
Project Management pertaining to the scope. Presentation to Eskom Design Review Team (DRT) Meeting.
Civil engineering to design the shared SS platform & layer works, foundations, access roads, drainage & cable trenches. Architectural drawings of the substation relay house. Electrical design of the Substation including equipment layouts, selection & specification, steelwork selection, outdoor lighting design, low voltage power distribution on the platform, lightning protection design, earth grid design (AutoGridPro), & control plant protection scheme selection. Line design & planning including PLS CADD simulations, including the underpass of the 765 kV and 400 kV lines which were presented at the Eskom Transmission Profile Review Meeting. Preparation of the control plant detailed design drawings (protection, control, supervisory, power supply, data retrieval, & security).
Engie VRE
Renewables Integration Study in Botswana’s Electric Power System
Client: Engie Impact Belgium SA,
Location: Botswana , Near Gaborone
Project start and end dates: March 2022 – December 2022
Project Description
Royal HaskoningDHV is appointed to do site surveys as inputs to a main study for renewable energy integration into the Botswana electrical network.
Services delivered
Interactive engagement with capacity planning studies (planning engineer).
Engagement with Environmental specialist on terrain related aspects.
Undertake site visits to review terrain in comparison to Google earth concepts.
Actual land availability to install +50MW plants.
Review and inspect grid connection points.
Review and inspect substation capacity requirements (new builds and extensions).
Prepare schematic diagrams and documents identifying and prioritizing sites based on location, accessibility, constructability and grid capacity.
Key challenges
Coordination of activities as the site is not in South Africa.